Completed CIP Projects

CIP 96048 ADA Improvements

Start Date: Winter 2026
End Date: Spring 2026
Project Manager: Ashley Morales
Status: Completed
Project Location(map)
The work involves the reconstruction of various curb ramps to meet ADA standards. 
On December 17, 2025 the City awarded a Public Works Contract to CJ Concrete Construction in the amount of $181,745 for the project. 

CIP 96058 FY 25-26 Concrete Improvements Project

Start Date: Fall 2025
End Date: Winter 2026
Project Manager: Ashley Morales
Status: Completed
Project Location(map)
The project involves the reconstruction of 14,500 sf of sidewalk, 500 sf of cross gutters, and 1,200 lf of curb and gutter. 
On October 15, 2025 the City awarded a Public Works Contract to Onyx Paving Company, Inc. in the amount of $309,000 for the project. 

CIP 96057 S Atlantic Blvd and E Emerson Ave Overlay and Slurry Seal Project

Start Date: Fall 2025
End Date: Winter 2026
Project Manager: Ashley Morales
Status: Completed
Project Location(map)
The project involves application of asphalt rubber hot mix and AC overlay on S. Atlantic Avenue from Harding to Newmark, Harding Avenue from S. Atlantic to De La Fuente Street and E. Emerson Avenue from N. Alhambra Avenue to N. Orange Avenue, and from Elizabeth Avenue to New Avenue; slurry seal on E. Emerson Avenue from N. Orange to Elizabeth Avenue; and all related concrete work.
On October 1, 2025 the City awarded a Public Works Contract to Onyx Paving Company, Inc. in the amount of $898,000 for the project. 

CIP 95058 Barnes Gym Painting

Start Date: Fall 2025
End Date: Fall 2025
Project Manager: Anthony Bendezu
Status: Completed
Project Location(map)
The project involves exterior painting of Barnes Park Gym. 
On August 20,2025 the City awarded a Public Works Contract to U.S National Corp. dba Jimenez Painting Company in the amount of $124,950 for the project. 

CIP 95056 Elder Gym and Langley Office Flooring

Start Date: Fall 2025
End Date: Fall 2025
Project Manager: Anthony Bendezu
Status: Completed
Project Location(map)
The project includes the replacement of carpet with vinyl flooring. The carpet has reached its useful service life and is need of replacement. 

CIP 95054 Cascades Epoxy Project

Start Date: Fall 2025
End Date: Fall 2025
Project Manager: Ziad MazboudiStatus: Completed
Project Location(map)
The project involves applying epoxy coating to the Cascades facility every three years to avoid black algae. 

CIP 95047 Barnes Pool Demo

Start Date: Spring 2025
End Date: Summer 2025
Project Manager: Ziad MazboudiStatus: Completed
Project Location(map)
The project involves demolition and filling of two pools at Barnes Park

CIP 95035 Various City Infrastructure Roof Repairs

Start Date: Winter 2025
End Date: Fall 2025
Project Manager: Nam TranStatus: Completed
Project Location(map)
The project includes asbestos abatement, roof removal and disposal, plywood sheet installation, PVC membrane roof system and flashing, fascia replacement, clay roof tile replacement, and the removal of existing wall wood shingles and installation of new metal wall panels at Elder gym, Garvey Ranch Museum, Langley Center and Garvey Ranch restrooms. 

On December 4, 2024 the City awarded a Public Works Contract to Best Contracting Services Inc. in the amount of $978,450 for the project. 

CIP 99011 Emerson Ave Parallel Pipeline

Start Date: Summer 2025
End Date: Fall 2025
Project Manager: Nam TranStatus: Completed
Project Location(map)
Installation of a new parallel sewer line to improve hydraulic capacity of the existing sewer system on Emerson Ave from  N Alhambra Ave to N Orange Ave and from Elizabeth Ave to New Ave. For a video update on the project, please click here
On May 7, 2025 the City awarded a Public Works Contract to GRBCON, Inc., in the amount of $647,141 for the project. 

CIP 96049 Pavement Improvements

Start Date: Spring 2025End Date: Summer 2025
Project Manager: Ashley MoralesStatus: CompletedProject Location(map)
The project involves the removal of existing pavement and the application of new pavement on various city streets. Also, the project will include concrete work such as the replacement of sidewalk, curb ramps, curbs, and gutters. For a video update on the project, please click here
On February 19, 2025 the City awarded Public Works Contract to Onyx Paving Company, Inc. in the amount of $4,146,240 for this project. 

CIP 99007 Russell St Reservoir

Start Date: December 2024End Date: Summer 2025
Project Manager: Ziad MazboudiStatus: CompletedProject Location(map)
The work includes application of protective coatings to interior surfaces and paint to exterior surfaces, including surface preparation, disinfection of interior surfaces and additions, replacement and modification of miscellaneous structural items to bring the structure into compliance with current safety and health codes, standards and regulations and other work necessary to accomplish the approved end result of totally protected and usable structures, including attachments, accessories and appurtenances

On September 18, 2024 the City awarded a Public Works Contract to Crosno Construction Inc. in the amount of $2,168,516 for this project. 

CIP 95013 Barnes Gym Restroom Upgrades

Start Date: Summer 2024End Date: Spring 2025
Project Manager: Nam TranStatus: CompletedProject Location(map)
The proposed work includes upgrades to the Barnes Park Gym restrooms and American with Disabilities (ADA) compliant renovations.

On June 18, 2024 the City awarded a Public Works Contract to U.S. Builders and Consultants Inc. in the amount of  $977,812 for this project.

CIP 96054 Concrete Improvements

Start Date: Winter 2025End Date: Spring 2025
Project Manager: Ashley MoralesStatus: CompletedProject Location(map)
The work includes the removal and replacement of concrete sidewalk, curb and gutter, and curb ramps at various locations Citywide. 
On November 20, 2024 the City awarded a Public Works Contract to Kalban Inc. in the amount of $651,197 for this project. 
On February 19, 2025 the authorized an amendment to the contract and awarded a Public Works Contract to CT&T in the amount of $230,957 for this project. 

CIP 95044 Barnes Gym Flooring

Start Date: Winter 2025End Date: Spring 2025
Project Manager: Nam TranStatus: CompletedProject Location(map)
The proposed project involves replacement of existing flooring at Barnes Gymnasium. Improvements consist of removal and installation of rubber base leveling layer, maple wood flooring and concrete slab repair as required. 

On November 20, 2024 the City awarded a Public Works Contract to R & S Flooring Solutions in the amount of $143,500 for this project.

CIP 96048 ADA Improvements

Start Date: Winter 2025End Date: Winter 2025
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)
The work includes the reconstruction of various curb ramps to meet current ADA standards. 
On November 6, 2024 the City awarded a Public Works Contract to Onyx Paving Company, Inc. in the amount of $169,000 for this project. 

CIP 96046 Monterey Pass Rd Street Rehabilitation

Start Date: December 2024End Date: Winter 2025
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)
The proposed work includes the road rehabilitation including paving and striping along Monterey Pass Road.
On October 2, 2024 the City awarded a Public Works Contract to Hardy and Harper, Inc. in the amount of $1,133,912 for this project. 

CIP 96012- Potrero Grande Renovation and Signal Improvements at Market Place and Markland

Start Date: Summer 2024End Date: Winter 2025
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes new landscaped median islands, pavement rehabilitation, in-fill tree planting in parkways, irrigation systems, ADA sidewalk and curb ramp improvements. Also, additional work  includes traffic signal improvements at intersections of Potrero Grande Drive with Markland Drive and Market Place Drive and all related work. 

On March 6, 2024 the City awarded a Public Works Contract to PTM General Engineering Services Inc. in the amount of $569,365 for the project. 

CIP 95014 Langley Restrooms Upgrade

Start Date: Summer 2024End Date: Fall 2024
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)

The proposed work includes upgrades to the Langley Center restrooms and American with Disabilities (ADA) compliant renovations.

On June 18, 2024 the City awarded a Public Works Contract to U.S. Builders and Consultants Inc. for this project, the estimated cost is $352,295.

CIP 96035- Cesar Chavez Ave Paving Project

Start Date: Summer 2024End Date: Fall 2024
Project Manager: Ziad MazboudiStatus: CompletedProject Location(map)
Project Location(map)
This project is in partnership with the LA County Public Works Department. The budget request is for the City's share of the project. The proposed scope of work in the City's jurisdiction includes: Cold Mill the existing Asphalt Concrete (AC) pavement full width 2 inches in depth; Construct an inch thick AC leveling course (D2-PG-64-10) over the entire cold milled surface; Construct 1 inch of Tire Ribber Modified Asphalt Concrete (C2-PG 64-28M) over the leveling course; Remove and replace one damaged bus pad.

CIP 99026- Sewer Manhole Rehabilitation

Start Date: Summer 2024End Date: Summer 2024
Project Manager:Anthony BendezuStatus: CompletedProject Location(map)

The project consists of the rehabilitation and coating of thirteen (13) manholes with varying depths from 7-feet to 11-feet. Including installation of temporary flow through sewage bypass system, manhole cleaning, surface preparation, mineral deposit removal, concrete spot repairs, infiltration mitigation, manhole coating and testing, traffic control and all related work. 

On March 26, 2024 the City awarded a Public Works Contract to Sancon Technologies Inc., in the amount of $156,045 for this project. 

CIP 99014 Cured in place Pipe Relining

Start Date: Fall 2023End Date: Summer 2024
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The project will consist of the rehabilitation of approximately 19,550 linear feet of 8-inch sanitary sewer pipeline using cured in place pipe lining. 
On August 16, 2023 the City awarded a Public Works Contract to Southwest Pipeline Trenchless Corp., in the amount of $823,699 for this project.

CIP 99012- Centralized Groundwater Treatment System

Start Date: August 2016End Date: Spring 2024
Project Manager: Frank HeldmanStatus: CompletedProject Location(map)
The Project consists of the design and construction of an Advanced Oxidation/Ultraviolet (AO/UV) water treatment system at the City's Delta Plant that is located in the City of Rosemead. The AO/UV facility uses state of the art equipment to remove contaminants in the groundwater. In 2021, the Centralized Groundwater Treatment System was further modified with the addition of a per-and polyfluoralkyl substance (PFAS) removal system. 

CIP 96036- SB1 Residential Street Rehabilitation

Start Date: Feb 2024End Date: Spring 2024
Project Manager: Peter ShiauStatus: CompletedProject Location(map)

The SB1 road improvement project is funded through the Road Maintenance and Rehabilitation Account (RMRA) fund. The work includes cold milling and removal of the existing asphalt pavement and constructing a rubberized asphalt overlay, adjusting utility covers to grade; constructing new ADA curb ramps; repairing residential sidewalk, restoring traffic striping and pavement markings; and providing and maintaining traffic control during construction. Impacted residents may experience temporary traffic control devices, lane closures, detours, parking enforcement and temporary limited driveway access. 

On November 15, 2023 the City awarded a Public Works Contract to All American Asphalt in the amount of $1,200,000 for this project. 

CIP 96031- Street Resurfacing

Start Date: Aug 2022End Date: Spring 2024
Project Manager: Anthony BendezuStatus: CompletedYear 1 Locations(map)
Year 2 Locations(map)
Year 3 Locations(map)

This project is divided into three phases and involves the removal of existing pavement and the application of new pavement on various city streets. Also, the project will include concrete work such as the replacement of sidewalk, curb ramps, curbs, and gutters. 

On June 15, 2022 the City awarded a Public Works Contract to All American Asphalt in the amount of $8,023,641 for Year 1 of the project and started in Summer 2022 and was completed in Summer 2023.

On June 7, 2023 the City awarded a Public Works Contract to All American Asphalt in the amount of $6,865,699 for Year 2 of the project and started in Summer 2023 and was completed in December 2023. 

On October 4, 2023 the City awarded a Public Works Contract to All American Asphalt in the amount of $1,625,000 for Year 3 of the project and started in November 2023 and was completed in Spring 2024.

CIP 95011- Library Improvements-Storyroom Expansion and Stained Glass

Start Date: Winter 2024End Date: Spring 2024
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)
The proposed work includes expansion of the storytime room at the Bruggermeyer Library and installation of donated stained glass windows. 
On February 7, 2024 the City awarded a Public Works Contract to U.S Builders and Consultants Inc. in the amount of $109,650 for this project.

CIP 95024- Highlands Park Big Playground Replacement

Start Date: Fall 2023End Date: Spring 2024
Project Manager:Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes the replacement of playground equipment. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground or the surrounding areas. 
On August 16, 2023  the City awarded a Public Works Contract to R.E. Schultz Construction, Inc. in the amount of $986,149 for this project. 

CIP 95019-Garvey Ranch Park Big Playground Replacement

Start Date: Fall 2023End Date: Spring 2024
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes the replacement of playground equipment. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground or the surrounding areas. 
On August 16, 2023  the City awarded a Public Works Contract to R.E. Schultz Construction, Inc. in the amount of $986,149 for this project. 

CIP 95022- Highlands Park Small Playground Replacement

Start Date: Fall 2023End Date: Spring 2024
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes the replacement of playground equipment. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground or the surrounding areas. 
On August 16, 2023 the City awarded a Public Works Contract to R.E. Schultz Construction, Inc. in the amount of $986,149 for this project.

CIP 96034- ATP Cycle 4

Start Date: Summer 2023End Date: Spring 2024
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)

The ATP Cycle 4 is part of the Active Transportation Program which consists of adding safety enhancements for pedestrians at various locations in the city. This includes restriping of streets, replacing and adding signs, adding solar powered flashing signs for pedestrian crosswalks, and adding ADA compliant pedestrian curb ramp with truncated domes. 

On December 7, 2022 the City awarded a Public Works Contract to California Professional Engineering Inc. in the amount of $1,360,870 for this project. 

CIP 95021- Bella Vista Park Playground Replacement

Start Date: Fall 2023End Date: Winter 2024
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes the replacement of playground equipment. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground or the surrounding areas. 
On August 16, 2023 the City awarded a Public Works Contract to R.E. Schultz Construction, Inc. in the amount of $986,149 for this project.

CIP 95020- Garvey Ranch Park Small Playground Replacement

Start Date: Fall 2023End Date: Winter 2024
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes the replacement of playground equipment. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground or the surrounding areas. 
On August 16, 2023 the City awarded a Public Works Contract to R.E. Schultz Construction, Inc. in the amount of $986,149 for this project.  

CIP 95018- Sequoia Park Small Playground Replacement

Start Date: Fall 2023End Date: Winter 2023
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes the replacement of playground equipment. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground or the surrounding areas. 

On August 16, 2023 the City awarded a Public Works Contract to R.E. Schultz Construction, Inc. in the amount of $986,149 for this project. 

CIP 95028- Barnes Park Amphitheater Seating

Start Date: Summer 2023End Date: December 2023
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes replacement of existing seating, installing LED lights, relocating trash containers, concrete repairs, and making American with Disabilities Act (ADA) compliant improvements. 

On July 5, 2023 the City awarded a Public Works Contract to Irwin Seating Company in the amount of $17,906.25 for this project. This project was completed in December 2023.

CIP 95017- Edison Trails Park Playground Replacement

Start Date: September 2023End Date: December 2023
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes the replacement of playground equipment. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground or the surrounding areas. 

On June 7, 2023 the City awarded a Public Works Contract to R.E. Schultz Construction, Inc. in the amount of $207,272 for this project. This project was completed in December 2023.

CIP 96039- FY22-23 Sidewalk Repairs

Start Date: Summer 2023End Date: December 2023
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed work includes constructing new ADA curb ramps, repairing residential sidewalk, bus pad replacements and other repairs as needed. Additionally nuisance trees that have caused infrastructure damaged may be removed and replaced with less intrusive trees.

On June 7, 2023 the City awarded a Public Works Contract to CT&T Concrete Paving, Inc., in the amount of $1,571,233 for this project. The project was completed in December 2023.

CIP 99023- Water Main Replacement-Northeast (Phase 3)

Start Date: Summer 2023End Date: December 2023
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The proposed project includes the replacement approximately 13,000 feet of existing water pipe with bigger size along the following streets: 1)Garvey from Alhambra to New; 2) Emerson from Garfield to Alhambra; 3) Lincoln from Emerson to Hellman; 4) Nicholson from Emerson to Hellman; 5) Garfield from Garvey to Hellman; 6) Garvey from Garfield to Alhambra; 7) Lincoln from Garvey to Emerson, and 8) Nicholson from Garvey to Emerson.
On March 1, 2023 the City awarded a Public Works Contract to Big Ben, Inc. in the amount of $2,251,600 for this project. This project was completed in December 2023.

CIP 96033- Catch Basin Retrofit Device Installation

Start Date: Spring 2023End Date: December 2023
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)
The catch basin device installation project consists of installing Connector Pipe Screen (CPS) units to city-owned and county-owned catch basins at various locations. These CPS devices are used to prevent the trash from entering the storm drain system during dry weather and moderate storm flows by keeping trash and debris inside the catch basin. Phase 1 included the installation of CPS units in 130 county-owned catch basins. Phase 2 includes installation at an additional 100 catch basin locations. 

On January 18, 2023 the City approved the First Amendment to Public Works Contract with United Storm Water to retrofit an additional 100 catch basins for a revised contract amount of $199,395. The project was completed in December 2023.

CIP 99025- Monterey Pass Road Water Main

Start Date: March 2023End Date: December 2023
Project Manager: Ziad MazboudiStatus: CompletedProject Location(map)
In December 2023, the City completed the emergency waterline construction project on Monterey Pass road from Vagabond Drive to Floral Drive.  The project included the construction of two parallel waterlines, replacing all water services, fire lines, fire hydrants and backflow devices.  The original waterline was a cement-lined steel pipe over fifty years old, that had been breaking regularly, resulting in water shutdowns affecting nearby businesses.

The new waterline is a C900 pipe, which is a PVC pressure pipe, manufactured to meet the needs of modern municipal water systems. 

The newly installed system provides various interconnects and a connection to the Vagabond pump station, which will result in a more robust and dependable system to serve the nearby residents and businesses. 

City staff worked closely with the contractor to keep businesses informed of the progress regularly and to update and coordinate when a shutdown was planned to avoid and minimize impact.

Paving of Monterey Pass Road was started in December 2024 and was completed in Winter 2025

CIP 96030- Slurry Seal 

Start Date: Summer 2022End Date: Spring 2024
Project Manager: Anthony BendezuStatus: CompletedYear 1 Locations(map)
Year 2 Locations(map)
Year 3 Locations(map)
This project will enhance the appearance and drivability of the street and will protect the base of the roadway from water damage and weathering as well as minimize the aging of the existing road and correct raveling and any other defects caused by weather elements. Impacted residents may experience temporary detours and limited driveway access. Please visit the Street Maintenance page for more information on the City's Slurry Seal Program

On June 15, 2022 the City awarded a Public Works Contract to Onyx Paving Company Inc.  in the amount of $848,000 for Year 1 of the project and started in Summer 2022 and was completed in Summer 2022.

On April 5, 2023 the City awarded a Public Works Contract to Onyx Paving Company, Inc. in the amount of $869,650 for  Year 2 of this project  started in Summer 2023 and was completed in Summer 2023. For more information on the project including the paving project schedule please click here.  

On October 4, 2023 the City awarded a Public Works Contract to Onyx Paving Company, Inc. in the amount of $1,400,000 for Year 3 of the project. Year 3 of this project started in Winter 2024 and was completed in Spring 2024. For more information on the project including the paving project schedule please click here

CIP 96036-SB1 Residential Street Rehabilitation

Start Date: Feb 2023End Date: Spring 2023
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The SB1 road improvement project is funded through the Road Maintenance and Rehabilitation Account (RMRA) fund. The work includes cold milling and removal of the existing asphalt pavement and constructing a rubberized asphalt overlay, adjusting utility covers to grade; constructing new ADA curb ramps; repairing residential sidewalk, restoring traffic striping and pavement markings; and providing and maintaining traffic control during construction. Impacted residents may experience temporary traffic control devices, lane closures, detours, parking enforcement and temporary limited driveway access.

On November 16, 2022 the City awarded a Public Works Contract to All American Asphalt in the amount of $869,422 for this project.

CIP 99010- Emerson Sewer Repair & Pipe Relining

Start Date: March 2023End Date: Spring 2023
Project Manager: Peter ShiauStatus: CompletedProject Location(map)
The project consists of rehabilitation of approximately 2,352 linear feet of 8-inch sanitary sewer main using Cured-In-Place Pipe (CIPP) lining method and it also includes spot repairs for approximately 85 linear feet of damaged sanitary sewer pipe.

On December 7, 2022 the City awarded a Public Works Contract to Sancon Technologies, Inc. in the amount of $155,229 for this project.

CIP 95027- Sierra Vista Park Resurfacing

Start Date: March 2023End Date: April 2023
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)
This project consists of resurfacing of existing Pickleball Court and Basketball Court including furnishing/installing new ProDunk basketball system and new pickleball sleeve/posts. 

On February 21, 2023 the City awarded a Public Works Contract to Trueline Construction & Surfacing, Inc in the amount of $26,306 for this project.

CIP 96004-HSIP Cycle 7

Start Date: March 2023End Date: Fall 2023
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)
The HSIP Cycle 7 project consists of Traffic Signal Modifications at Garfield Ave; Garfield Ave and Hellman Ave; Alhambra Ave/Almansor St and Hellman Ave, construction of curb ramps, signs and pavement markers, striping and related work.

On March 2, 2022 the city awarded a Public Works Contract to PTM General Engineering in the amount of $1,030,500 for this project.

CIP 96028-HSIP Cycle 9

Start Date: Summer 2023End Date: Fall 2023
Project Manager: Anthony BendezuStatus: CompletedProject Location(map)
The HSIP Cycle 9 project consists of Traffic Signal Modifications at Garfield Ave, full replacement of traffic poles and mast arms to provide a protected left turn, construction of curb ramps, signs and pavement markers, striping and related work. 

On May 3, 2023 the City awarded a Public Works Contract to PTM General Engineering Services, Inc. in the amount of $485,694 for this project.